Free change-order worksheet
Use the free change-order calculator when the job scope changes and the price needs to be explained before it goes to the customer. It keeps direct cost, markup, and contract impact visible.
Formula
Change order total = sum((labor hours x labor rate) + material cost) + markup
Worked example
Calculation
The worksheet shows the customer-facing price and the contract-impact percentage before the team writes the final reviewed change order.
Upgrade timing
Stay with the free tool for one-off planning. Move to a paid workspace when the same work needs persistence, review handoff, branded output, or team coordination.
You need saved change orders tied to jobs and customer records.
You want reviewed proposal or invoice handoff instead of copying values manually.
You need project-manager and estimator visibility into scope changes across active jobs.
Related
FAQ
No. It is a calculator and worksheet for pricing and review. Use your contract language and legal process before presenting a binding change order.
Yes. The free calculator lets you set the markup or overhead percentage and shows direct cost, markup, total change amount, and new contract total.